Extensive sections of steel platework are required to be replaced as can be seen in this
photo from the 15th May 2010.
By early December the smokebox and front tubeplate had already been removed
6th November 2009, 7820's boiler was loaded and transported to Riley & Son for contract repair.
With the boiler removed the frames were steam cleaned in anticipation of the removal of
the brake and spring gear, it makes the job much more pleasant!
An internal view of the front tubeplate taken inbetween needle gunning the inside of the barrel.
An internal view of the longitudinal, transverse and crown stays taken inbetween needle
gunning the inside of the barrel.
A good days work by one of our regular volunteers, cylinder cladding carefully removed,
marked/labelled ready for storage.
After!
Before